This page last changed on Nov 04, 2013 by tm.

This is the log of the Waveglider Tex

2013 Mar 26

  • Launch and Recovery training with Lorraine of LRI

2013 Mar 27 to 2013 Apr 2

  • Shakeout cruise, ctd

2013 Jun 5 to 2013 Jun 6

  • LRAUV acoustic test

2013 Jun 12 (changed from 11th) to 2013 Jun 17

  • Launch using the RV John Martin (Paragon down for repairs)
  • HotSpot testing
  • Recovered by RV John Martin for for DOEST

2013 Jun 20 to 2013 Jun 28

  • DARPA LRAUV acoustics

2013 Aug 22 to 2013 Aug 28

  • Brian / Brett (thanks!) recovered Tex since LR indicated the the C&C need to be pressurized. Looks like someone vented or opened the C&C while it was in the storage container June/July
    • Note: scuffing on the side looks like it had been struck by a boat, not scratches but material from the offending boat
  • C&C pressurized to 4ish psi by Paul Coenen, WGMS shows 128 to 129

2013 Aug 28

  • Firmware Update thru Xbee from LR (Kim Hosaka)
    • FCC - 2.00.995
    • IPIB - 1.3.365
    • PIB - 2.1.395
    • Power Manager - 0038.236
    • Bubble Controller - 044.015
    • C&C Pressure holding 128 to 130 depending on temperature

2013 Aug 28 to 2013 Oct 22

  • Waveglider recovered by request of HotSpot team Sep 24, redeployed Oct 1 (2)?
Document generated by Confluence on Feb 03, 2026 16:13